Answer: Four days Explanation: It should take 3-4 days to do this large of a space. It would depend on whether you are doing closet space, how may rooms, and if you are replacing the pad or not. |
Jim Handy Lawn & Handyman Services |
Answer: One day or less Explanation: depends on type of installed glue stretch |
Winbergs Flooring Service |
Answer: Four days Explanation: job calculates to 36 hrs in a square room. doors, closets, ex..add time to job |
The honea do specialist |
|
ProMatcher |
Answer: Two days Explanation: it will take 2 days to install a full house |
99 CARPETS |
Answer: One day or less Explanation: 2000 sq ft of carpet should be done within 6 hours |
Pro-Carpet Care (469) 647-1508 |
Answer: One day or less Explanation: 1 day |
BCI Flooring Brokers Inc |
|
ProMatcher |
Answer: Two days Explanation: Start to finish including tear out install and clean up typically this takes two days to complete this is 200 yards of carpet. |
The Floor Guys |
Answer: Two days Explanation: 222.22 yds of carpet should take about 8 hrs. If it empty no furniture with furniture 2 days tops! |
Floors 2 UR Doors |
Answer: Two days Explanation: Average 10 to 13 hrs |
Empire Restoration & Cleaning Services |
|
ProMatcher |
Answer: One day or less Explanation: This job would take me 12-14 hrs |
Carpet Mike |
Answer: Three days Explanation: I wouldn't schedule anything for at least 3 days |
SPECIALIZED FLOOR COVERINGS |
Answer: One day or less Explanation: Most jobs are completely done in the same day |
Drapery and Blind cleaning |
|
ProMatcher |
Answer: One day or less Explanation: One day total time. |
DfwCarpetClean |
Answer: Three days Explanation: This should take typically about 2-3days depending on seam layout, type of carpeting and furniture and floor preperation |
Southwest Florida Floors |
Answer: Two days Explanation: One day to remove furniture existing flooring and the lay the new pad and tackless strips.
One day to seam and install the carpeting.
Will come with a lifetime warranty |
A Beautiful Estate Inc |
|
ProMatcher |
Answer: Two days Explanation: It can take up to two days depending if u have to tear out olf flooring or not |
V&H HOME IMPROVEMENT |
Answer: One day or less Explanation: If it is empty it should take 1 full day |
The Plan |
Answer: Two days Explanation: length of time contains variables as if new construction or occupied |
McDonough Flooring |
|
ProMatcher |
Answer: Two days Explanation: 2 day's maybe more if furniture moving is involved or there is removal of old carpeting,also time depends on how hard or easy material is to work with. |
All Flooring |
Answer: Two days Explanation: You can install about 1,000 feet a day unless some unforeseen circumstances arise. 2,000 should take you about two days. |
American Veterans Fence Company |
Answer: Two days Explanation: Plan for two days, it could take longer depending on the job. |
Rite Rug |
|
ProMatcher |
Answer: One day or less Explanation: If we have to remove existing flooring it will take longer. |
FLOORS ON A BUDGET LLC. |
Answer: One day or less Explanation: I am answering based on having purchased the same carpet for the entire home |
Sarita's Cleaning Services, LLC |
Answer: Two days Explanation: same answer a good carpet installer should be able to complete this project at the time allotted |
Colorful Homes Painting And Restoration |
|
ProMatcher |
Answer: One day or less Explanation: depends on if the house is empty but we would say 8-12 hours. |
R&R Carpet Cleaning |
Answer: Three days Explanation: I do not install carpet |
Two Girls and A Crew Cleaning |
Answer: One day or less Explanation: In new construction or an empty home 2000 square feet of carpet usually includes all rooms and can be completed most times within one day. In an owner occupied home with furniture moving and removal of existing carpet you should allow two days for completion. |
Floor Decor |
|
ProMatcher |
Answer: One day or less Explanation: it depend the number of carpet crew
usually it take two day with only two installer |
Home Improvement Crew LLC |
Answer: Two days Explanation: It's depends on the layout |
Whites Flooring |
Answer: One day or less Explanation: Again a crew of 3-5 people could do this under 8 hours. |
Churley Flooring LLC |
|
ProMatcher |
Answer: One day or less Explanation: Same questions are applied. Still should take less than one day |
installyourfloors.com |
Answer: Three days Explanation: Considering existing flooring will need to be removed and hauled away, furniture moving and installation of carpet over stairs |
Project Contracting, LLC |